In a short 2.5 month timeframe, the Dragon team successfully delivered (multiple??) wellpad buildings to an oil sands site in Northern Alberta.
- Install all electrical gear in the building, wire all gear, QAQC process and commissioning
- Install 12 sections of MCC, lighting panels, battery bank and charger, instrument air
- Package 6 PLC cabinets, 8 VFDs and 8 Transformers including interior/exterior cable tray and supports
- Reconnection of buildings on-site, final QAQC, start-up and commissioning
- 2,400 manhours